How to read the result
- How the quantity is worked out: the area times the finished depth is the volume you want after the dirt is rolled. Dirt is measured in three states: bank (in the ground), loose (dug and delivered) and compacted (placed and rolled). The page converts your finished volume back to bank, then forward to loose, which is what a truck carries.
- Why you order more than length × width × depth: loose dirt is bulkier than compacted dirt. For earth, dry packed with 20% shrinkage, 22.2 yd³ of finished fill is 27.8 yd³ in the bank and 34.7 yd³ loose, before any extra. Set the shrinkage to 0 to see the plain area × depth.
- How the weight is found: the weight of dirt does not change when it is dug, loaded or compacted, only its volume does. So the tons come from the bank volume times the bank weight (3,203 lb/yd³ here), and the loose weight shown is that weight spread over the larger loose volume.
- What the shrinkage figure means: shrinkage is the percentage reduction from bank volume to compacted volume. The shrinkage factor is the share left after that reduction: 1 − shrinkage ÷ 100. At 20% shrinkage, 100 cubic yards in the bank becomes 80 cubic yards compacted, so the factor is 0.80. This is different from a density specification such as 95% Proctor. Use the shrinkage specified for your project; 20% is our starting value (the handbook’s worked example), not a standard.
- What this page does not do: it does not set the compaction level, the lift thickness or the fill material for a foundation, wall or pavement. Those come from the engineer’s specification. Use the Topsoil Calculator for topsoil cover over the fill.
To turn the volume into tons for a different material, use the Cubic Yards to Tons Calculator. Topsoil to cover the finished fill? The Topsoil Calculator works out the order. This page gives the quantity only: the compaction level and the fill material for any structure come from the engineer's specification.
Worked example
An area 40 ft by 30 ft raised 6 in after compaction with dry packed earth, 20% shrinkage, a 10% extra and a 10 yd³ truck load (your own load goes here).
- Area = 40 × 30 = 1,200 ft²
- Finished volume = 1,200 × (6 ÷ 12) = 600.0 ft³ = 600.0 ÷ 27 = 22.22 yd³
- Bank volume = 22.22 ÷ (1 − 20%) = 27.78 yd³
- Loose volume = 27.78 ÷ load factor 0.80 = 34.72 yd³
- With a 10% extra: 34.72 × 1.10 = 38.2 yd³ (29.2 m³)
- Weight = 27.78 yd³ × 3,203 lb/yd³ × 1.10 = 48.9 tons (44.4 tonnes)
- Truck loads = 38.2 yd³ ÷ 10 yd³ = 4 loads (rounded up)
Other shapes work the same way. A triangle with a 40 ft base and a 30 ft height is half the area, so the order is 19.1 yd³. An L made of the 40 × 30 ft area plus a 20 × 10 ft strip needs 44.6 yd³. A quarter acre (10,890 ft²) at the same depth needs 346.6 yd³, about 444.0 tons. To add several areas at the same depth, press "Add another area" and enter the next one.
If the same fill is left loose, so the 6 in is the loose depth, the order is 24.4 yd³ and 31.3 tons. With 10% shrinkage instead of 20%, the order is 34.0 yd³ and 43.5 tons.
These are the same numbers the calculator shows when it first loads.
Method and formulas
Area: rectangle = length × width · circle = π × (diameter ÷ 2)² · triangle = ½ × base × height · L-shape = L1 × W1 + L2 × W2 · several areas = their sum
1 acre = 43,560 ft² · 1 hectare = 10,000 m²
Finished volume = area × depth · Bank volume = finished ÷ S.F., where S.F. = 1 − shrinkage ÷ 100
Loose volume = bank ÷ L.F. (load factor, from the weight table) · Volume to order = loose × (1 + extra ÷ 100)
Weight = bank volume × bank weight × (1 + extra ÷ 100) · Loads = volume to order ÷ truck load, rounded up · 1 yd³ = 27 ft³ = 0.7646 m³
- S.F.
- Shrinkage factor: compacted volume ÷ bank volume
- L.F.
- Load factor: bank volume ÷ loose volume, 100% ÷ (100% + % swell)
- Bank weight
- Weight of the dirt in the ground, per cubic yard (lb/yd³) or cubic metre (kg/m³)
Assumptions and limits
- The result is the quantity of fill to order. It is not a compaction specification: the required density, lift thickness and test method come from your project specification or soils report.
- Dirt is measured in three states (Caterpillar handbook): bank (as it lies in the ground), loose (dug and delivered, swelled) and compacted (placed and rolled). The weight does not change between them, the volume does.
- The shrinkage when compacted is 20% by default, the handbook's worked-example value, not a standard. It depends on the soil and the compaction required. Type your own.
- Weights are the Caterpillar handbook table values for the fill you pick; weight varies with moisture, grain size and compaction, so your supplier's figures (loose weight and bank weight) can replace them.
- The extra for waste and uneven ground is yours to set (10% to start); it is not a standard value.
- Does not choose or check the compaction level (percent Proctor), the lift thickness or the fill material for a structure. Structural fill for a foundation, retaining wall or pavement is specified by the engineer.
- Does not work out cut and fill balance, haul distance, topsoil cover over the fill, or settlement of soft ground under the fill.
- Uses one shrinkage value for the whole job, not a different one for each layer or soil.
- Several areas share one finished depth. An area at a different depth needs its own run.
- Does not trace an area on a map.
- Rock fill, crushed stone and gravel base are different materials: use the Crushed Stone, Gravel or Road Base calculators.
- No price is supplied: a cost appears only from a price you type.
Reference tables
| Material | Bank weight | Loose weight | Load factor | Swell |
|---|---|---|---|---|
| Earth, Dry packed | 3,200 (1,900) | 2,550 (1,510) | 0.8 | 25% |
| Earth, Wet excavated | 3,400 (2,020) | 2,700 (1,600) | 0.79 | 27% |
| Earth, Loam | 2,600 (1,540) | 2,100 (1,250) | 0.81 | 23% |
| Clay, Natural bed | 3,400 (2,020) | 2,800 (1,660) | 0.82 | 22% |
| Clay & gravel, Dry | 2,800 (1,660) | 2,400 (1,420) | 0.85 | 18% |
| Sand & clay, Loose | 3,400 (2,020) | 2,700 (1,600) | 0.79 | 27% |
| Sand & gravel, Dry | 3,250 (1,930) | 2,900 (1,720) | 0.89 | 12% |
| Sand, Dry, loose | 2,700 (1,600) | 2,400 (1,420) | 0.89 | 12% |
Source: Caterpillar Performance Handbook, Edition 50 (form AEXQ3330, © 2021), Section 25 "Elements of Production", pages 25-2 and 25-3, and Tables section "Weight of Materials", page 27-6. The handbook says weight varies with moisture content, grain size, degree of compaction, etc.
| Finished depth | Finished yd³ | 10% shrinkage | 20% shrinkage | 30% shrinkage |
|---|---|---|---|---|
| 2 in | 6.2 | 8.6 | 9.6 | 11.0 |
| 4 in | 12.3 | 17.1 | 19.3 | 22.0 |
| 6 in | 18.5 | 25.7 | 28.9 | 33.1 |
| 8 in | 24.7 | 34.3 | 38.6 | 44.1 |
| 12 in | 37.0 | 51.4 | 57.9 | 66.1 |
Source: Calculated with the EngiFormula fill dirt engine (method v1.1). 1 yd³ = 27 ft³, from the exact definitions 1 ft = 0.3048 m and 1 yd = 0.9144 m, and 1 lb = 0.45359237 kg, NIST Special Publication 811 (2008 edition), Appendix B. Bank, loose and compacted volume and the load factor follow the Caterpillar Performance Handbook, Edition 50, pages 25-2 and 25-3; weights are from page 27-6.
| State | What it means |
|---|---|
| Bank (BCY or BCM) | Material as it lies in the natural bank state, before it is dug |
| Loose (LCY or LCM) | Material that has been dug or otherwise disturbed and has swelled because of the spaces between its pieces |
| Compacted (CCY or CCM) | Material that has been compacted and has become more dense |
Source: Caterpillar Performance Handbook, Edition 50 (form AEXQ3330, © 2021), Section 25 "Elements of Production", pages 25-2 and 25-3, and Tables section "Weight of Materials", page 27-6. The handbook says weight varies with moisture content, grain size, degree of compaction, etc.
Common uses
Raising or levelling a yard
Enter the area and the finished depth you want, and leave the fill compacted. Use “left loose” only if you will not roll it.
A building pad or driveway edge
Use the length and width of the pad, or the area if you know it. Take the shrinkage from the project specification and keep the page’s note that compaction levels come from the engineer.
Backfill around a structure
Enter the area and the depth of the backfill after compaction. For a trench or excavation, the volume dug out is a separate figure.
Checking a delivery quote
Compare the yards and tons on a quote with the result here. Type your supplier’s bank and loose weights and the truck load to match their figures.
Seeing what shrinkage does
Change the shrinkage and watch the order move. The table above shows loose yards for 1,000 ft² at several depths and shrinkage values.
Frequently asked questions
How much fill dirt do I need?
Multiply the area by the finished depth, divide by 27 for cubic yards, then allow for compaction and swell and add an extra for waste. For 1,200 ft² at 6 in, that is 22.22 yd³ finished, 34.72 yd³ loose, and 38.2 yd³ with 10% extra.
How much does fill dirt compact?
It depends on the soil, its moisture and the compaction required. The Caterpillar Performance Handbook defines the shrinkage factor as compacted volume divided by bank volume and says it is estimated or taken from the job plans or specification; its worked example uses 0.80 for dry clay, which is the 20% this page starts with. It is not the same as percent compaction (Proctor), which specifies density. Use the figure from your specification or soils report.
How much does a cubic yard of fill dirt weigh?
The handbook lists 2,550 lb per loose cubic yard and 3,200 lb per bank cubic yard for dry packed earth, and other values for wet earth, loam, clay and sand-gravel (see the table). Weight varies with moisture, grain size and compaction, so ask your supplier and type their figures into the calculator.
How many cubic yards is 10 tons of dirt?
Divide the tons by the loose weight per yard. At the page’s starting values the loose weight is about 1.28 tons per cubic yard, so 10 tons is about 7.8 loose cubic yards. For another material use the Cubic Yards to Tons Calculator.
How many yards of dirt fit in a dump truck?
It depends on the truck and its weight limit, so the page assumes none: enter the loose cubic yards your supplier loads. The 10 yd³ on the page is an example only. The loads shown are the order divided by your load, rounded up.
Do I add extra for settling when I order fill dirt?
The page already allows for the shrinkage when the fill is compacted. The extra is for waste, spillage and uneven ground and is your choice; 10% is a practical starting value, not a standard.
Sources and references
- Caterpillar Inc., Caterpillar Performance Handbook, Edition 50 (form AEXQ3330, © 2021), Section 25 pages 25-2 and 25-3 (bank, loose and compacted volume, swell, load factor, shrinkage factor) and Tables section page 27-6 (weight of materials).
- NIST Special Publication 811, Guide for the Use of the International System of Units (SI), 2008 edition, Appendix B (exact values for the inch, foot, yard and pound).
- Area relations (rectangle, circle, triangle and L-shape): plane geometry, as set out in the Method section above.
- Acre and hectare: 1 acre = 43,560 ft² with the international foot (NIST, U.S. Survey Foot: Revised Unit Conversion Factors); 1 hectare = 10,000 m².
About this calculator
Scope and disclaimer
Calculates the quantity of fill dirt (cubic yards or cubic metres, tons or tonnes, truck loads) for one or up to 5 areas (rectangle, circle, triangle, L-shape or a known area in ft², acres, m² or hectares) and a finished depth, allowing for the shrinkage when it is compacted. It does not set the compaction level or check any design.