How to read the result
- Strip, pad or round: a strip footing runs under a wall, a pad sits under a post or column, and a round footing or pier is a cylinder. Pick the one that matches your plan, or add up to three groups for a job that has more than one.
- Footing depth is concrete depth: the depth here is the thickness of the concrete, not how far below the ground the trench goes.
- Building outline: measure the length and width of the footing outline to the centre of the footing, and the page adds 2 × (length + width), so corners are not counted twice. Add the total length of any interior wall footings in the optional field.
- Why an allowance, and why the half yard: a ready-mix supplier advises a 10% allowance for uneven sub-grade and spillage, then rounding up to the closest half yard. A trench dug wider or deeper than the form takes more, so raise the allowance if yours is.
- What this page does not decide: how wide or deep a footing must be depends on the soil, the loads, the frost depth and the local building code. Take those sizes from your plan, your building department or an engineer.
The footing needs steel as well: the Rebar Calculator gives the bars to buy and their weight. To price the concrete order, use the Concrete Cost Estimator.
Worked example
A strip footing around a 30 × 20 ft outline, 16 in wide and 8 in deep, with 10% extra, using 80 lb bags.
- Run length = 2 × (30 + 20) = 100 ft
- Cross-section = (16 ÷ 12) × (8 ÷ 12) = 0.889 ft², so 0.889 ft³ per ft of strip
- Volume = 100 × 0.889 = 88.9 ft³ = 88.9 ÷ 27 = 3.29 yd³
- With 10% extra: 3.29 × 1.1 = 3.62 yd³ (2.77 m³) = 97.8 ft³; rounded up to the next half yard, order 4.0 yd³ (3.06 m³)
- Bags = 97.8 ÷ 0.6 ft³ per 80 lb bag = 163.0, rounded up to 163 bags (80 lb)
Add 6 round piers, 12 in across and 8 in deep, as a second group: each holds 0.524 ft³, so 6 hold 3.14 ft³, and the total with 10% extra is 3.75 yd³, order 4.0 yd³ (3.06 m³).
The first four steps are the same numbers the calculator shows when it first loads.
Method and formulas
Strip: V = run length × width × depth, run length = 2 × (outline length + outline width) + interior length
Pad: V = length × width × depth × number · Round: V = π × d² ÷ 4 × depth × number
Total = (sum of the groups) × (1 + w ÷ 100) · Order = total in yd³ rounded up to the next ½ yd³
Bags = total ÷ yield per bag, rounded up · 1 yd³ = 27 ft³ = 0.764554857984 m³
- width, depth, d
- Footing width and depth of concrete, and diameter of a round footing
- number
- Number of identical pads or piers in the group
- w
- Waste and over-excavation allowance, %
- yield
- Volume of mixed concrete one bag makes, from the manufacturer's data sheet
Assumptions and limits
- Each footing group has a uniform cross-section over its whole length.
- Strip length from the outline is the perimeter of the rectangle entered; corners are not counted twice and wall openings are not deducted.
- Dimensions are those of the concrete poured (the form), not of the trench; a trench dug wider or deeper than the form is covered only by the allowance.
- Reinforcing steel and anchor bolts are ignored; the volume they displace is small and sits inside the allowance.
- Bag yields are QUIKRETE Concrete Mix No. 1101 figures; other brands list their own yields.
- Gives the quantity of concrete for footing sizes the reader already has. It does not size a footing: width, depth, reinforcement, bearing on the soil and frost depth come from the plan, the soil report and the local building code or an engineer.
- Default dimensions are examples to show the arithmetic, not a recommendation.
- Not a design check, a permit document or a take-off from drawings; stepped footings, footings with a stem wall, bell bases and sloping trenches are split into simple shapes by the reader.
- Does not work out rebar, excavation, formwork or gravel; use the linked calculators when they are live.
Reference tables
| Depth | 12 in wide | 16 in wide | 20 in wide | 24 in wide |
|---|---|---|---|---|
| 6 in | 1.85 | 2.47 | 3.09 | 3.70 |
| 8 in | 2.47 | 3.29 | 4.12 | 4.94 |
| 10 in | 3.09 | 4.12 | 5.14 | 6.17 |
| 12 in | 3.70 | 4.94 | 6.17 | 7.41 |
Source: Calculated with the EngiFormula footing engine (method v1.0). Unit conversion uses the exact definitions 1 in = 25.4 mm, 1 ft = 0.3048 m and 1 yd = 0.9144 m, NIST Special Publication 811 (2008 edition), Appendix B. Before any allowance.
Round footings and piers
| Diameter | ft³ at 8 in deep | ft³ at 12 in deep | 80 lb bags at 12 in deep |
|---|---|---|---|
| 8 in | 0.233 | 0.349 | 1 |
| 10 in | 0.364 | 0.545 | 1 |
| 12 in | 0.524 | 0.785 | 2 |
| 16 in | 0.931 | 1.396 | 3 |
| 18 in | 1.178 | 1.767 | 3 |
| 24 in | 2.094 | 3.142 | 6 |
Source: Calculated with the EngiFormula footing engine (method v1.0). Unit conversion uses the exact definitions 1 in = 25.4 mm, 1 ft = 0.3048 m and 1 yd = 0.9144 m, NIST Special Publication 811 (2008 edition), Appendix B. Before any allowance. Bags use the QUIKRETE No. 1101 yield for the selected bag.
Bags per cubic yard
| Bag size | Yield per bag (approx.) | Bags per cubic yard |
|---|---|---|
| 40 lb | 0.3 ft³ | 90 |
| 50 lb | 0.375 ft³ | 72 |
| 60 lb | 0.45 ft³ | 60 |
| 80 lb | 0.6 ft³ | 45 |
Source: QUIKRETE Concrete Mix No. 1101 data sheet, revised October 2022, page 1: each yield is "approximately". Bags per cubic yard = 27 ft³ ÷ yield, rounded up.
Charts and diagrams
Common uses
- Strip footing under a house, garage or shed: choose Strip, enter the outline length and width, the footing width and depth.
- Deck, porch or pergola piers: choose Round footing or pier, enter the diameter, depth and number of piers; add a pad group for any square footings.
- Spot footings under posts and columns: choose Rectangular pad and enter its length, width, depth and how many.
- Checking a quote: compare your order line and bag count with the supplier's figures at the same allowance.
Frequently asked questions
How do I calculate the concrete for a footing?
Multiply the length, width and depth, all in feet (divide inches by 12), to get cubic feet, then divide by 27 for cubic yards. For the 100 ft strip above, 16 in wide and 8 in deep, that is 100 × 0.889 = 88.9 ft³, or 3.29 yd³, before the allowance.
How many bags of concrete do I need for a footing?
Divide the volume in cubic feet by the yield of one bag and round up. For the strip above with 10% extra, that is 97.8 ÷ 0.6 = 163.0, so 163 bags (80 lb). The QUIKRETE No. 1101 data sheet gives an 80 lb bag a yield of approximately 0.6 ft³, which is 45 bags per cubic yard. Yields are approximate and differ by brand.
How much extra concrete should I order for a footing?
A ready-mix supplier, Superior Materials, advises a 10% allowance for uneven sub-grade, spillage and similar losses, then rounding up to the closest half yard. The calculator starts at 10% and shows the half-yard order line. A trench dug wider or deeper than the form needs more, so raise the allowance if yours is. It is easier to cancel a truck than to add one.
How wide and deep should a footing be?
This page does not decide that. The width and depth of a footing depend on the soil it bears on, the loads it carries, the frost depth and the local building code. Take them from your plan, your building department or an engineer; then enter them here to get the quantity of concrete.
How much concrete do I need for deck footings?
Choose Round footing or pier, enter the diameter and depth from your deck plan, and the number of piers. For 6 piers 12 in across and 8 in deep, that is 3.14 ft³ before the allowance. The pier size and depth come from your deck plan and permit, not from this page.
How do I find the length of a strip footing around a house?
Use the building outline option: enter the outline length and width and the page works out 2 × (length + width). For 30 × 20 ft that is 100 ft. Add the total length of footings under interior walls in the optional field, or choose "Total length I already know" and type the run yourself.
Does rebar change how much concrete I need?
Not enough to matter here. Reinforcing steel displaces a small share of the volume, and the page ignores it; the allowance covers it. How much rebar a footing needs is a separate question that depends on the design.
Should I use bags or ready-mix for a footing?
The bag count shows the scale of the job: the strip above takes 163 bags (80 lb). Ready-mix is ordered by the cubic yard, rounded up to the half yard, so compare the order line and your supplier's price with the cost of the bags and the work of mixing them. Suppliers may have a minimum load, so ask before you order.
Is this a foundation concrete calculator, or a concrete calculator for deck footings?
Both, for footings. It covers strip, pad and round footings, including the piers of a deck. For a foundation with walls, work out the walls separately with the Concrete Volume Calculator and add them. The sizes come from your plan, not from this page.
Sources and references
- QUIKRETE International, Inc., QUIKRETE Concrete Mix No. 1101 data sheet, revised October 2022, page 1 (approximate yield per bag).
- Superior Materials LLC, How much concrete do I need? (concrete calculator page), the ordering note on the 10% allowance and rounding up to the closest 1/2 yard. A supplier's advice, not a standard.
- NIST Special Publication 811, Guide for the Use of the International System of Units (SI), 2008 edition, Appendix B (exact values for the inch, foot and yard).
- Area and volume relations: plane and solid geometry, as set out in the Method section above.
About this calculator
Scope and disclaimer
Calculates the quantity of concrete for footings whose size the reader already has. It does not size a footing or check it against soil, loads or the building code. The bag count uses the QUIKRETE No. 1101 yields; another brand can differ, so check the bag.
This calculator gives information and preliminary estimates only. It is not professional design advice and does not replace the governing code, product instructions or a qualified professional's judgement for your project.