- Cut (bank volume): the soil you dig, measured as it lies in the ground. Here 2,000 ft² × 2 ft = 4,000 ft³ = 148.1 yd³.
- Fill (compacted volume): the finished, rolled fill in place. Here 1,000 ft² × 1.5 ft = 1,500 ft³ = 55.6 yd³.
- Bank soil needed for the fill: soil shrinks when it is compacted, so the fill takes more bank soil than its finished volume. At 20% shrinkage that is 55.6 yd³ ÷ 0.80 = 69.4 yd³.
- Net balance: cut minus the bank soil the fill needs. Positive is a surplus to haul away, negative is a shortfall to bring in. Here it is +78.7 yd³.
- Loose volume and loads: dug soil swells, so the trucks carry more than the bank balance. Dry packed earth swells 25.0%, so 78.7 yd³ becomes 98.4 yd³, which is 8 loads of 14 yd³. Enter your own truck.
- Grid of spot depths: choose "Grid of spot depths" and type, at each point of a square grid, how far the ground is above (+, cut) or below (−, fill) the finished level. The page splits each square into two flat triangles and adds up the cut and the fill, splitting a triangle at the zero line where it has both. On a 3 × 3 grid at 20 ft with depths 2, 1, 0 / 1, 0, −1 / 0, −1, −2 ft (a tilted flat plane) the cut and the fill are each 533.33 ft³ (19.8 yd³), the same as two pyramids of 800 ft² base and 2 ft height.
- What this page does not do: it takes one cut and one fill, each with an average depth, volumes you already have, or a grid of spot depths. It does not read contours, maps or cross sections, and it gives no cost or haul distance. For the volume of a single pit or trench use the Excavation Calculator.
A positive balance means soil to haul away, a negative one soil to bring in. To find the volume of a single pit or trench first, use the Excavation Calculator. To order fill dirt by area and depth, use the Fill Dirt Calculator, and if you only have an area and a depth the Cubic Yard Calculator gives the yards. This page supports a grid of spot depths as well as average depths and known volumes. For earthwork quantities directly from contours, cross sections or a larger survey model, use the design drawings or survey software.
Worked example
A site with a cut of 2,000 ft² averaging 2 ft deep and a fill of 1,000 ft² averaging 1.5 ft deep (finished depth), in dry packed earth, with 20% shrinkage and a 14 yd³ truck (your own figures go here).
- Cut = 2,000 × 2 = 4,000 ft³ ÷ 27 = 148.1 yd³ (113.3 m³)
- Fill, compacted = 1,000 × 1.5 = 1,500 ft³ ÷ 27 = 55.6 yd³ (42.5 m³)
- Bank soil for the fill = 55.6 yd³ ÷ (1 − 20%) = 69.4 yd³ (53.1 m³)
- Balance = 148.1 yd³ − 69.4 yd³ = +78.7 yd³ (+60.2 m³), a surplus to haul away
- Loose volume = 78.70 yd³ × (1 + 25.0% swell) = 98.4 yd³ (75.2 m³)
- Truck loads = 98.4 yd³ ÷ 14 yd³ = 8 loads (rounded up)
If the cut is only 0.5 ft deep, the balance becomes −32.4 yd³, so shortfall: soil to bring in: 40.5 yd³ loose, 3 loads. In natural-bed clay (swell 22.0%) the first example swells to 96.0 yd³ instead of 98.4 yd³. With no shrinkage the fill would need only 55.6 yd³ of bank soil instead of 69.4 yd³.
These are the same numbers the calculator shows when it first loads.
Method and formulas
Cut = cut area × average cut depth · Fill (compacted) = fill area × average fill depth
Grid: each square → 2 triangles of area A = s² ÷ 2 · one sign: V = A × (h1 + h2 + h3) ÷ 3 · mixed signs: lone-corner part = A × h³ ÷ [3 (h − ha)(h − hb)], the rest is the difference
Bank soil for the fill = fill ÷ S.F., with S.F. = 1 − shrinkage ÷ 100
Balance = cut − bank soil for the fill (positive = surplus, negative = shortfall)
Loose volume = |balance| × (1 + swell) · Swell = 1 ÷ L.F. − 1 · Truck loads = loose volume ÷ truck load, rounded up · 1 yd³ = 27 ft³ = 0.7646 m³
- S.F.
- Shrinkage factor: compacted volume ÷ bank volume of the same soil
- L.F.
- Load factor: bank volume ÷ loose volume, from the Caterpillar table
- h, s
- Grid depth at a point (+ cut, − fill) and the grid spacing
- Bank, loose, compacted
- The soil in the ground, after digging, and after rolling in the fill
Assumptions and limits
- The cut and the fill are each one area with one average depth; the average depth is the reader's own figure (from levels, a drawing or a survey).
- Grid of spot depths: the ground is flat on each triangle between three neighbouring points, so a real surface that bends between points is approximated; a closer spacing follows it better.
- Cut volume is in the ground (bank); fill volume is the finished, compacted volume in place.
- One soil type and one shrinkage figure apply to the whole job; the fill is made from the cut soil, and any shortfall is imported soil of the same type.
- Shrinkage 20% (factor 0.80) is the handbook's worked-example value used as a labelled starting value; swell comes from the handbook load factors or the reader's own percentage.
- Topsoil stripping, rock, unsuitable material, haul distance and stockpiling are not included.
- A quantity helper for a balance estimate, not a survey: it does not read a grid, contours or cross sections, and it does not replace earthwork quantities from the design drawings or a geotechnical report.
- No cost, haul distance or mass-haul diagram.
- No soil classification or slope safety verdict; the page does not decide shoring or protective systems.
- Swell and shrinkage are planning values; use your geotechnical report, project specification or hauler data when you have it.
Reference tables
| Shrinkage | Shrinkage factor S.F. | Bank soil needed (yd³) | Extra over the fill (yd³) |
|---|---|---|---|
| 0% | 1.00 | 100.0 | 0.0 |
| 10% | 0.90 | 111.1 | 11.1 |
| 15% | 0.85 | 117.6 | 17.6 |
| 20% | 0.80 | 125.0 | 25.0 |
| 25% | 0.75 | 133.3 | 33.3 |
| 30% | 0.70 | 142.9 | 42.9 |
Source: Calculated with the EngiFormula cut and fill engine (method v1.1). Bank soil needed = compacted volume ÷ shrinkage factor, where the shrinkage factor S.F. = compacted ÷ bank volume (Caterpillar Performance Handbook, Edition 50, Section 25, pages 25-2 and 25-3). 1 yd³ = 27 ft³, from the exact definitions 1 ft = 0.3048 m and 1 yd = 0.9144 m, NIST Special Publication 811 (2008 edition), Appendix B.
| Material | Load factor | Swell | Bank weight | Loose weight |
|---|---|---|---|---|
| Earth, Dry packed | 0.8 | 25.0% | 3,200 (1,900) | 2,550 (1,510) |
| Earth, Wet excavated | 0.79 | 26.6% | 3,400 (2,020) | 2,700 (1,600) |
| Earth, Loam | 0.81 | 23.5% | 2,600 (1,540) | 2,100 (1,250) |
| Clay, Natural bed | 0.82 | 22.0% | 3,400 (2,020) | 2,800 (1,660) |
| Clay and gravel, Dry | 0.85 | 17.6% | 2,800 (1,660) | 2,400 (1,420) |
| Sand and clay, Loose | 0.79 | 26.6% | 3,400 (2,020) | 2,700 (1,600) |
| Sand and gravel, Dry | 0.89 | 12.4% | 3,250 (1,930) | 2,900 (1,720) |
| Sand, Dry, loose | 0.89 | 12.4% | 2,700 (1,600) | 2,400 (1,420) |
Source: Caterpillar Performance Handbook, Edition 50 (form AEXQ3330, © 2021), Section 25 "Elements of Production", pages 25-2 and 25-3 (bank, loose and compacted volume, swell, load factor L.F. = 100% ÷ (100% + % swell), shrinkage factor) and Tables section "Weight of Materials", page 27-6. Swell here is 1 ÷ L.F. − 1. The handbook says weight varies with moisture content, grain size, degree of compaction, etc.
Common uses
Grading a building pad or a yard
Enter the area you will cut down and the area you will build up, with the average depth of each, to see whether the site balances or soil has to leave or arrive.
Bringing in fill for a low area
When the fill is bigger than the cut gives, the shortfall tells you how much to order. The Fill Dirt Calculator then turns it into loose yards or tons with a cost from your own price.
Planning spoil trucks
Enter your truck size to see the loads for soil going out or coming in.
Using volumes from your drawings
Choose “Volumes I already know” and enter the cut volume and the compacted fill volume from your survey or earthwork quantities. The page then does the shrinkage, swell and trucks.
Checking a quote
Compare a contractor’s haul-off or import figure with the balance here, and check whether it is quoted per bank yard, loose yard or compacted yard.
Frequently asked questions
How do you calculate cut and fill?
Multiply the cut area by its average depth for the cut, and the fill area by its average depth for the fill, then compare them. For a 2,000 ft² cut 2 ft deep that is 4,000 ft³ or 148.15 yd³, and for a 1,000 ft² fill 1.5 ft deep it is 1,500 ft³ or 55.56 yd³. Shrinkage then changes how much bank soil the fill takes, as the Method section shows.
What is the difference between cut and fill?
Cut is soil removed to lower the ground, and fill is soil added to raise it. On the same site, soil from the cut can be used for the fill, and what is left over is hauled away or what is missing is brought in.
What are swell and shrink factors in earthwork?
Swell is how much soil grows in volume when it is dug (loose soil takes more room than bank soil). Shrinkage is how much it reduces when it is compacted. The Caterpillar Performance Handbook gives a load factor for each material, and the swell is one divided by that factor, minus one. For dry packed earth the load factor is 0.8, a swell of 25.0%. The handbook gives no single shrinkage figure for fill; this page starts at 20% (the handbook’s worked example) and you replace it with your project figure.
How much extra soil do I need to make a compacted fill?
Divide the finished fill volume by the shrinkage factor. At 20% shrinkage the factor is 0.80, so 55.6 yd³ of compacted fill takes 69.4 yd³ of bank soil. The table above shows other shrinkage values for 100 yd³ of fill.
What does a positive or negative balance mean?
A positive balance means the cut gives more bank soil than the fill needs, so the surplus is hauled away. A negative balance means the fill needs more than the cut gives, so the shortfall is brought in. The page shows which one applies and the loose volume to move.
How many truck loads of dirt will I need to haul or import?
Divide the loose volume by what one truck carries and round up. At 14 yd³ per truck, 98.4 yd³ is 8 loads. The truck size on the page is an example: ask your hauler what their trucks carry. Imported soil is assumed to be the same type as the cut.
What is the grid method for cut and fill?
The grid method divides the site into squares, finds the cut or fill depth at each corner from the existing and the finished levels, and adds up the volumes of the squares. This calculator does it for up to 8 × 8 points: choose “Grid of spot depths”, enter the spacing and the depth at each point (+ for cut, − for fill), and it splits each square into two flat triangles, so a square that is partly cut and partly fill is split at the zero line rather than averaged. For a larger grid, a survey program or drawing quantities, choose “Volumes I already know” and enter the volumes to get the balance, swell, shrinkage and truck loads.
Sources and references
- Caterpillar Inc., Caterpillar Performance Handbook, Edition 50 (form AEXQ3330, © 2021), Section 25 pages 25-2 and 25-3 (bank, loose and compacted volume, swell, load factor, shrinkage factor) and Tables section page 27-6 (weight of materials and load factors).
- NIST Special Publication 811, Guide for the Use of the International System of Units (SI), 2008 edition, Appendix B (exact values for the inch, foot and yard).
- Volume of a prism (area times depth): solid geometry, as set out in the Method section above.
About this calculator
Scope and disclaimer
The net balance of one cut and one fill, each with an average depth or a known volume, or of a grid of spot depths up to 8 × 8 points, with swell, shrinkage and truck loads. Not a survey, contour, map or cross-section tool, and not a cost or haul-distance tool.
This calculator gives information and preliminary estimates only. It is not professional design advice and does not replace the governing code, product instructions or a qualified professional's judgement for your project.