Excavation Cost Calculator

Enter the size of the cut and your own prices for digging, hauling and the dump. You get the volume in the ground, the loose volume the trucks carry, the truck loads, a cost line for each, and your total per cubic yard. No price is built in.

  • Your own prices, no hidden rates
  • Quote check per cubic yard
  • Cited swell (Caterpillar ed. 50)
  • Price by yard or by hour
  • US and metric

Enter the size of the cut

Units
ft
ft
ft
H : 1 V
yd³

For a trench, the length of the run. Measure the bottom of the cut.

0 means vertical sides. 1 means 1 horizontal for each 1 vertical (45°). Your engineer or the competent person on site sets the slope, not this page.

Swell is how much the soil grows when it is dug, worked out from the Caterpillar Performance Handbook load factors. Use your own figure if you have one.

Loose cubic yards one truck carries. 14 is an example: use your own truck.

Enter your prices

This page has no price list. Type the prices from your quote or your own costs. A line you leave blank is left out of the total.

$ per yd³
$ per load
$ per yd³
$
%
$

Depends on the machine, the soil and the site. Use your own figure.

A flat amount for machine delivery, permits, locating utilities, shoring, backfill and similar. This page does not work them out.

An allowance for rock, water or surprises. It is your judgement, not a figure from a standard.

Shows what the quote works out to per cubic yard in the ground, next to your own total.

Estimated excavation total from your prices

Enter your prices below

Volume to dig (in the ground)
177.8 yd³
Volume to haul (loose, after swell)
222.2 yd³
Swell used
25.0%
Truck loads
16 loads
Machine hours
Hourly method only
Digging
Not included
Hauling
Not included
Dump fees
Not included
Fixed costs
Not included
Contingency
—
Your total per cubic yard in the ground
Enter your prices below
Your quote per cubic yard in the ground
Enter a quote to compare
Quote against your total
Enter a quote and your prices to compare

You dig about 177.8 yd³ in the ground. Once dug it swells to about 222.2 yd³, which is what the trucks carry and the dump takes. Every price, rate and percentage is the one you enter: backfill, shoring, rock, water, permits and locating utilities are not included unless you add them under fixed costs. This is a budget, not a quote.

Show the working

  1. Volume in the ground = 40 × 30 × 4 ft ÷ 27 = 177.8 yd³
  2. Loose volume = 177.8 yd³ × (1 + 25% swell) = 222.2 yd³
  3. Truck loads = 222.2 yd³ ÷ 14 yd³ per load, rounded up = 16

What you can do with this calculator

  1. Work out the excavation cost from your own prices. Enter the size of the dig and your digging, hauling and dump prices to get the total.
  2. See the cost per cubic yard of your dig. The total is divided by the cubic yards in the ground, so you can compare it with any price per yard.
  3. Compare a contractor's quote with your own figures. Type the quote to see it per cubic yard next to your total and how far apart they are.
  4. Price the haul and the dump fees for the spoil. Truck loads and the loose cubic yards, worked out from the swell of your soil, go to the haul and dump lines.
  5. Price the digging by the yard or by the machine hour. Use a price per cubic yard, or a machine rate with your output per hour.

How to read the result

  • Digging is priced on the volume in the ground (bank volume): that is the length times the width times the depth of the cut. Most unit prices and quotes are per cubic yard in the ground, so that is the figure the digging line uses.
  • Hauling and dump fees follow the loose volume: dug earth is bulkier than earth in the ground. For dry packed earth the swell is 25.0%, so 177.8 yd³ in the ground becomes 222.2 yd³ in the trucks. Hauling is charged per truck load, rounded up, and a dump usually charges for what arrives.
  • Unit price or machine hours: price the digging per cubic yard, or enter an all-in machine and operator rate with the cubic yards the machine digs per hour. The page shows the machine hours. Use whichever your quote is in.
  • Fixed costs and contingency: set-up, machine delivery, permits, locating utilities, backfill, shoring and similar go in one flat amount, because this page does not work them out. Contingency is a percentage you choose for rock, water or surprises.
  • The quote check: a contractor’s total divided by the cubic yards in the ground gives a price per yard you can compare with your own total per yard. A big gap is a reason to ask what the quote includes.
  • Why there is no built-in price: published excavation prices differ by many times with the size of the job, the region, the soil, access and where the soil goes, so any price on this page would mislead. Type your own, or the ones you were quoted.
  • What this page does not decide: it works out quantities and a budget only. It does not classify the soil, choose a safe side slope, or decide on shoring or other protection. That is the job of the competent person on site and the rules that apply. For the volume without prices, use the Excavation Calculator.

To see the volume, swell and truck loads without any prices, use the Excavation Calculator. To balance cut and fill on a site and see how much must leave, use the Cut and Fill Calculator. For a pipe trench, the Trench Calculator adds bedding and backfill. This page is a budget from the prices you enter, not a quote: backfill, shoring, rock, water, permits and locating utilities go under fixed costs, and the side slope and protection for the cut come from the competent person on site.

Worked example

A cut 40 ft by 30 ft at the bottom, 4 ft deep, vertical sides, dry packed earth, 14 yd³ truck. The prices below are made up to show the arithmetic. Use your own.

  1. Volume in the ground = 40 × 30 × 4 = 4,800 ft³ = 4,800 ÷ 27 = 177.8 yd³
  2. Loose volume = 177.78 yd³ × (1 + 25.0% swell) = 222.2 yd³
  3. Truck loads = 222.2 yd³ ÷ 14 yd³ = 16 loads (rounded up)
  4. Digging = 177.78 yd³ × $10.00 per yd³ (made-up) = $1,777.78
  5. Hauling = 16 loads × $120.00 per load (made-up) = $1,920.00
  6. Dump fees = 222.22 yd³ × $15.00 per yd³ (made-up) = $3,333.33
  7. Fixed costs = $500.00 (made-up), so the subtotal is $7,531.11
  8. Contingency = $7,531.11 × 10% = $753.11
  9. Total = $8,284.22, which is $46.60 per yd³ in the ground

A quote of $4,800.00 for the same dig is $27.00 per yd³, which is $3,484.22 less than your total: worth asking what it leaves out.

If the digging is priced by the hour instead, at $150.00 an hour and 20 yd³ an hour, the machine runs 8.9 h and the digging line is $1,333.33.

The calculator itself starts with every price blank, so it shows the quantities until you enter your prices.

Method and formulas

Volume in the ground: vertical sides = length × width × depth; round hole = π × (diameter ÷ 2)² × depth; sloped sides as in the Excavation Calculator
Loose volume = volume in the ground × (1 + swell) · Swell = 1 ÷ L.F. − 1 · Truck loads = loose volume ÷ truck load, rounded up · 1 yd³ = 27 ft³ = 0.7646 m³
Digging = volume in the ground × price per yd³, or (volume in the ground ÷ output per hour) × machine rate per hour
Hauling = truck loads × price per load · Dump fees = loose volume × fee per yd³ · Subtotal = digging + hauling + dump fees + fixed costs
Contingency = subtotal × percentage · Total = subtotal + contingency · Total per yd³ = total ÷ volume in the ground

L.F.
Load factor: bank volume ÷ loose volume, from the Caterpillar table
Fixed costs
A flat amount you enter: set-up, machine delivery, permits and similar
Contingency
A percentage of the subtotal that you choose

Assumptions and limits

  • The cut is a plain box (or round hole) with a flat bottom and one uniform side slope on every side; you enter the size of the bottom.
  • Bank volume is the volume in the ground before digging; loose volume is the volume after the soil is dug and has swelled; swell comes from the Caterpillar handbook load factor of the chosen soil, or the percentage you type.
  • Every price, rate, output and percentage is entered by the reader; the page contains no price list and no regional cost data.
  • Digging is priced on bank volume, hauling on whole truck loads, dump fees on loose volume; soil that stays on site is handled by leaving the haul and dump prices blank.
  • Backfill, compaction, shoring, dewatering, rock, permits and locating utilities are not worked out; the reader can add them under fixed costs.
  • A budget and quantity helper, not a quote or a safety tool: it does not classify soil, choose a side slope, or decide on shoring, benching or other protective systems. A competent person on site does that under the rules that apply.
  • The result is only as good as the prices entered; published price ranges for excavation differ by 20 times or more with job size, region, soil, access and disposal, so the page supplies none.
  • Plain shapes only: no varying depth, uneven ground, benches, ramps, stepped sides or several sections; use the Cut and Fill Calculator to balance cut and fill.
  • Swell values are planning values; use your geotechnical report or hauler data when you have it.

Reference tables

Volume in the ground in cubic yards for common sizes and depths (vertical sides, bottom size)
Size at the bottom3 ft deep6 ft deep8 ft deep
10 × 10 ft11.122.229.6
20 × 10 ft22.244.459.3
30 × 20 ft66.7133.3177.8
40 × 30 ft133.3266.7355.6

Source: Calculated with the EngiFormula excavation cost engine (method v1.0). The prices in the third table are made up to show the arithmetic; they are not market prices. 1 yd³ = 27 ft³, from the exact definitions 1 ft = 0.3048 m and 1 yd = 0.9144 m, NIST Special Publication 811 (2008 edition), Appendix B.

Swell of earth, clay and sand-gravel, from the handbook load factor
MaterialLoad factorSwell
Earth, Dry packed0.825.0%
Earth, Wet excavated0.7926.6%
Earth, Loam0.8123.5%
Clay, Natural bed0.8222.0%
Clay and gravel, Dry0.8517.6%
Sand and clay, Loose0.7926.6%
Sand and gravel, Dry0.8912.4%
Sand, Dry, loose0.8912.4%

Source: Caterpillar Performance Handbook, Edition 50 (form AEXQ3330, © 2021), Section 25 "Elements of Production", pages 25-2 and 25-3 (bank and loose volume, swell, load factor L.F. = 100% ÷ (100% + % swell)) and Tables section "Weight of Materials", page 27-6. Swell here is 1 ÷ L.F. − 1. The handbook says weight varies with moisture content, grain size, degree of compaction, etc.

The 40 × 30 ft, 4 ft deep example at three made-up digging prices (hauling, dump fees, fixed costs and contingency as in the worked example)
Digging priceDigging lineTotalTotal per yd³ in the ground
$6 per yd³ (made-up)$1,066.67$7,502.00$42.20
$10 per yd³ (made-up)$1,777.78$8,284.22$46.60
$14 per yd³ (made-up)$2,488.89$9,066.44$51.00

Source: Calculated with the EngiFormula excavation cost engine (method v1.0). The prices in the third table are made up to show the arithmetic; they are not market prices. 1 yd³ = 27 ft³, from the exact definitions 1 ft = 0.3048 m and 1 yd = 0.9144 m, NIST Special Publication 811 (2008 edition), Appendix B.

Common uses

A foundation, basement or pool

Enter the bottom size and depth of the cut, then your digging price and what it costs to haul the soil away and dump it. Add anything else, such as backfill, under fixed costs.

A trench for a pipe or a footing

Use the rectangle with the length of the run. For the bedding and backfill of a pipe trench, the Trench Calculator is the better start.

Checking a quote

Type the contractor’s total to see it per cubic yard in the ground. Ask whether their price is per bank yard or per loose yard, and what it includes.

Soil that stays on site

If the soil stays on site, leave the hauling price and the dump fee blank, and they are left out of the total.

Frequently asked questions

How much does excavation cost per cubic yard?

There is no single figure. Published ranges differ by many times, for example from a few dollars to over a hundred dollars per cubic yard, because the cost depends on the size of the job, the region, the soil, access, the distance to the dump and minimum charges. This page does not guess: enter your own digging price and it shows your total per cubic yard. In the worked example, with made-up prices, it is $46.60 per yd³.

How do you calculate excavation cost?

Multiply the volume in the ground by your digging price, add hauling (truck loads times the price per load) and dump fees (loose volume times the fee), then fixed costs and a contingency. For the 40 by 30 ft, 4 ft deep example that is $8,284.22 with the made-up prices.

What is the difference between bank volume and loose volume, and which do I pay for?

Bank volume is the earth in the ground. Loose volume is the same earth once dug, when it takes more room. Digging is usually priced on bank volume; trucks and dump fees follow loose volume. Check whether a price is per bank yard or per loose yard.

How many truck loads of dirt will my excavation produce?

Divide the loose volume by what one truck carries and round up. At 14 yd³ per truck, 222.2 yd³ is 16 loads. The truck size on the page is an example: ask your hauler what their trucks carry.

What affects the cost of excavation?

Soil and rock, depth, water, access for the machine, the distance to the dump and its fees, minimum charges, utilities, permits and shoring. This page prices the dig, the haul and the dump from your numbers; everything else goes in fixed costs or contingency.

Is it cheaper to dig by the hour or by the yard?

Neither is always cheaper. A price per yard puts the risk of slow digging on the contractor; an hourly rate puts it on you. With made-up numbers, $150.00 an hour at 20 yd³ an hour is $1,333.33 for this dig, against $1,777.78 at $10.00 a yard. Enter both of your own to compare.

Does the cost include backfill, shoring or rock?

No. They are not worked out here. Add them under fixed costs, or ask for them as separate lines in a quote.

Sources and references

  • Caterpillar Inc., Caterpillar Performance Handbook, Edition 50 (form AEXQ3330, © 2021), Section 25 pages 25-2 and 25-3 (bank and loose volume, swell, load factor) and Tables section page 27-6 (weight of materials and load factors).
  • NIST Special Publication 811, Guide for the Use of the International System of Units (SI), 2008 edition, Appendix B (exact values for the inch, foot and yard).
  • Volume of a box, a cylinder and a frustum: solid geometry, as set out in the Method section above. All prices, rates, outputs and percentages are the reader’s own; the prices in the worked example are made up.

About this calculator

Method version: 1.0 Last technical update:

Scope and disclaimer

The volume of a plain rectangular or round cut, the loose volume and truck loads, and a cost built from the reader's own digging, hauling, dump, fixed-cost and contingency figures. Not a quote, price list, safety, soil classification, shoring or backfill tool.

This calculator gives information and preliminary estimates only. It is not professional design advice and does not replace the governing code, product instructions or a qualified professional's judgement for your project.